 Post an article  get this group's latest topics as an RSS feed add this group's latest topics to your My MSN content add this group's latest topics to your My Yahoo content  add this group's latest topics to your Google content  YahooMyWeb Yahoo!  Google Google  Windows Live Favorites Windows Live  del.icio.us del.icio.us  digg digg  Add to Netscape Netscape
Subject Author Date
Generating a PO in HQ based on Reorder info. mbonin 06-04-2007
Posted by mbonin on June 4, 2007, 10:00 am
Please log in for more thread options
We have set re order points for items at the store level and can gerate POs
at the store level based on this reorder info.

Is it possible to generate PO's for slected stores from HQ based on a stores
reorder info. Thus far I cannot figure out how to do this and it is really
frustrating as we would like all ordering to be done at the HQ level.

Thanks,
Matt

Posted by mbonin on June 4, 2007, 12:12 pm
Please log in for more thread options
I have figured out that I can achieve this by selcecting "create a p.o. based
on supplier"

One question is if different stores have different restocking levels does HQ
recognize this?

Thanks,
Matt

"mbonin" wrote:

> We have set re order points for items at the store level and can gerate POs
> at the store level based on this reorder info.
>
> Is it possible to generate PO's for slected stores from HQ based on a stores
> reorder info. Thus far I cannot figure out how to do this and it is really
> frustrating as we would like all ordering to be done at the HQ level.
>
> Thanks,
> Matt

Posted by mbonin on June 4, 2007, 3:44 pm
Please log in for more thread options
Ok So now i am encountering this problem when i go to generate a p.o based on
re order info in HQ

First I select the store i would like to work with...

In that store:

Product A has a reorder point of 12 and a restock level of 48

Product B has a reorder point of 24 and a restock level of 96

Actual inventory for product A and B is 0 right now in that store and the
suppliers MQP and minimum order = 0 in both cases

In store ops when i create a p.o. based on reorder it orders 48 units of A
and 96 units of B which is correct

In HQ when i create the PO it orders 48 untis of Product A and 120 units of
product B.

Why is this? Could it be that HQ is trying to balance the inventory bewteen
all stores or am i missing something?

Thanks
Matt










In HQ when i create a p.o. based on reorder it orders

"mbonin" wrote:

> We have set re order points for items at the store level and can gerate POs
> at the store level based on this reorder info.
>
> Is it possible to generate PO's for slected stores from HQ based on a stores
> reorder info. Thus far I cannot figure out how to do this and it is really
> frustrating as we would like all ordering to be done at the HQ level.
>
> Thanks,
> Matt

Posted by Glenn Adams [MVP - Retail Mgmt on June 4, 2007, 5:55 pm
Please log in for more thread options
Check the MPQ for the item for that supplier in HQ - it may be different
than what was set at the store.

Glenn Adams
Tiber Creek Consulting
http://www.tibercreek.com
glenn@tibercreek.com
----------------------------------------------
Please DO NOT respond to me directly but post all responses here in the
newsgroup so that all can share the information.


mbonin wrote:
> Ok So now i am encountering this problem when i go to generate a p.o based on
> re order info in HQ
>
> First I select the store i would like to work with...
>
> In that store:
>
> Product A has a reorder point of 12 and a restock level of 48
>
> Product B has a reorder point of 24 and a restock level of 96
>
> Actual inventory for product A and B is 0 right now in that store and the
> suppliers MQP and minimum order = 0 in both cases
>
> In store ops when i create a p.o. based on reorder it orders 48 units of A
> and 96 units of B which is correct
>
> In HQ when i create the PO it orders 48 untis of Product A and 120 units of
> product B.
>
> Why is this? Could it be that HQ is trying to balance the inventory bewteen
> all stores or am i missing something?
>
> Thanks
> Matt
>
>
>
>
>
>
>
>
>
>
> In HQ when i create a p.o. based on reorder it orders
>
> "mbonin" wrote:
>
>> We have set re order points for items at the store level and can gerate POs
>> at the store level based on this reorder info.
>>
>> Is it possible to generate PO's for slected stores from HQ based on a stores
>> reorder info. Thus far I cannot figure out how to do this and it is really
>> frustrating as we would like all ordering to be done at the HQ level.
>>
>> Thanks,
>> Matt

Similar ThreadsPosted
Report with reorder info and sales November 14, 2005, 11:16 am
udating reorder cost, reorder number, and supplier October 31, 2007, 4:52 am
Barcode Generating May 4, 2006, 5:54 am
Need Help in Generating Report August 15, 2008, 5:04 pm
QSrule for generating Journal October 18, 2005, 12:58 pm
Over Short before generating Z Report March 2, 2007, 12:16 pm
Report Generating Question June 2, 2007, 4:01 pm
Problem Generating PO Number May 7, 2008, 10:32 am
Generating Invoices to be tendered at a later date November 3, 2005, 8:07 am
Detailed sales generating inaccurate/inconsistent data June 12, 2006, 12:53 pm

Contact Us | Privacy Policy
This site is not affiliated with Intuit - makers of Quickbooks and Quicken software
This site is not affiliated with Sage Software - makers of Peachtree accounting software
XML SitemapXML Sitemap